Guide to RTM Site Prep and Delivery
This guide explains the major steps involved in preparing for the delivery and placement of a STAR RTM home, including what STAR handles, what the homeowner coordinates and what to expect before and after delivery.
Key Takeaways
How the STAR RTM Home Process Works
STAR RTM homes are constructed away from the customer’s property and then transported to the prepared site by an experienced building mover.
The level of completion can vary according to the signed sales contract. Depending on the selected scope, STAR may complete the structural shell, roof, interior components and other agreed features. Customers may also choose to manage selected finishing work themselves, such as flooring or cabinetry, where permitted by the contract and construction process.
The home’s layout may be customized based on the customer’s needs and the approved design. Foundation requirements are incorporated into the drafting process and reviewed for construction use.
While STAR provides guidance, plans and contractor referrals, the homeowner remains the central coordinator for most work occurring on the property.
Who Does What?
What STAR Handles Before Your RTM Home Leaves the Yard
- Drafting and design development for the RTM home
- Confirms colour + interior selections
- Incorporating the selected foundation type into the home plans
- Obtaining the required structural design or engineering documentation for STAR’s construction scope
- Constructing the home to the agreed stage of completion
- Coordinating inspections required for the home while it is being constructed, including applicable framing and mechanical inspections
- Providing plans and specifications required by the homeowner’s foundation contractor and other trades
- Providing general guidance about site preparation and delivery planning
- Providing referrals or a contractor list for services such as foundations, decks, moving and other trades
- Coordinating the release or pickup of the completed home with the homeowner’s selected building mover
Note: The customer’s sales contract should remain the definitive source for what STAR will construct and what is included in the home price.
What the Homeowner Is Responsible For
- Confirming that the property can accommodate the home
- Providing accurate property and access information
- Securing municipal or local permits and approvals
- Hiring a foundation contractor
- Selecting the foundation type in consultation with STAR and applicable professionals
- Completing excavation, foundation construction and curing
- Preparing the driveway and delivery area
- Clearing trees, branches and other obstacles
- Addressing overhead utility lines or other overhead obstructions through the appropriate utility or contractor
- Hiring an experienced building mover
- Confirming delivery-route feasibility with the mover
- Coordinating the mover, foundation contractor, utilities and other trades
- Arranging well, septic, sewer, water and electrical services as applicable
- Confirming utility entry and connection locations
- Paying transportation, site preparation, utility and contractor costs that are not included in the STAR contract
- Managing post-placement connections and finishing work
- Ensuring heating and HVAC systems are supplied and installed
- Completing remaining occupancy, inspection or permit requirements
Note: The homeowner is responsible for arranging and coordinating work outside STAR’s contracted home-construction scope, including hiring and managing site contractors.
Know Your Responsibilities Before Construction Begins
Before signing contractor agreements or starting excavation, the homeowner should understand:
- What is included in the STAR sales contract
- What will be completed at STAR’s construction yard
- What must be completed on the property
- Which permits and inspections are required locally
- Which plans the foundation contractor needs
- Who is responsible for the delivery route
- Who will hire and pay the building mover
- Who will coordinate utility work
- What must happen after placement
- Whether the homeowner will manage the project or hire outside project-management support
Project Responsibilty Matrix
| Project Activity | STAR | Homeowner | Third Party |
|---|---|---|---|
| RTM home design and drafting | Lead | Review and approve | Engineer or designer as required |
| RTM home construction | Lead | Inspectors as required | |
| Property assessment information | Support | Lead | Building mover leads |
| Delivery-route review | Support as applicable | Coordinate | Building mover leads |
| Municipal permits | Support with documentation | Lead | Municipality approves |
| Foundation selection | Provide home requirements | Select and coordinate | Engineer and foundation contractor |
| Excavation and foundation | Hire and coordinate | Foundation contractor | |
| Driveway and site clearing | Lead | Site contractor as needed | |
| Building mover | Referral or pickup coordination as applicable | Hire and manage | Mover |
| Utility planning and connections | Provide relevant home information | Lead | Utility providers and trades |
| Placement-day site coordination | Confirm release requirements | Lead | Mover and site contractors |
| Post-placement completion | Contract and warranty scope only | Lead | Local trades |
Your 5-Step STAR RTM Home Preparation and Delivery Plan

Step 1: Assess Your Property and Delivery Access
Confirm Your Lot Can Accommodate the Home
Begin by considering whether the property has enough space for the selected home, the foundation and the equipment required during delivery.
Assessment factors may include (movers determine these items with the homeowner):
- Driveway width
- Road approach
- Turning space
- Slope and grade
- Ground conditions
- Distance from the road to the foundation
- Space around the foundation
- Trees and vegetation
- Overhead wires and other obstructions
- Access for the transport vehicle and placement equipment
Inspect the Delivery Route
The building mover should inspect and approve the delivery route before the move is finalized. This can include public-road access, private approaches, driveway dimensions, turns, clearances and access to the foundation.
STAR and the homeowner may provide relevant property information, but the experienced building mover is responsible for evaluating the transportation route and identifying delivery requirements within the mover’s scope.

Step 2: Secure Permits, Approvals and Foundation Requirements
Confirm Required Permits
The homeowner is responsible for contacting the applicable municipality, planning district or authority to confirm permits and approvals.
Requirements may include:
- Building permits
- Development or zoning approvals
- Foundation permits
- Well or septic approvals
- Electrical permits
- Plumbing permits
- Mechanical permits
- Permits or inspections associated with final utility connections
- Occupancy-related approvals
Requirements vary by location, project type and authority having jurisdiction.
Secure Financing and Purchase Approval
Before construction can begin, homeowners must obtain the required financing and purchase approvals.
STAR does not order materials or begin construction on an RTM home until financing requirements and purchase approvals have been completed.
Depending on the lender, financing for an RTM project may differ from a traditional home purchase. Some lenders may use construction-style financing, staged funding or other approval processes specific to RTM projects.
Before Moving Forward
Homeowners should:
- Speak with their lender early in the planning process
- Understand any RTM-specific financing requirements
- Confirm what documentation the lender requires
- Understand how and when funds will be released
- Review the payment schedule outlined in their STAR purchase agreement
- Ensure financing and approvals are in place before expecting construction to begin
Construction of the RTM home cannot begin until the required financing and purchase approvals have been completed.
Review STAR Plans and Specifications
Once the design process begins, review the plans and specifications with STAR and share the approved information with the foundation contractor, building mover and applicable trades.
Plans may be needed to:
- Confirm home dimensions
- Prepare formal foundation quotes
- Establish foundation openings and support requirements
- Coordinate utility-entry locations
- Confirm orientation on the property
- Plan excavation and site access
- Coordinate delivery and placement
Stock plans may help contractors prepare preliminary budget estimates, but the project-specific plans should guide final pricing and construction.
Confirm Foundation Requirements Before Excavation
Before excavation begins:
- Confirm the foundation dimensions and structural requirements
- Ensure the foundation contractor is using the correct approved plans
- Confirm utility penetrations and entry points
- Confirm the home’s orientation
- Coordinate requirements with the building mover
- Identify any access needed around the foundation
- Confirm inspection and approval requirements
Do not excavate or construct the foundation using unapproved dimensions or assumptions. Confirm the project-specific plans and requirements first.

Step 3: Prepare the Foundation, Driveway and Site
Choose the Appropriate Foundation
Depending on the home, property and approved design, foundation options may include:
| Foundation Type | Key Considerations |
|---|---|
| Full basement | Excavation, drainage, access, wall and support design, stairs, utility locations and coordination with the home layout |
| Crawl space | Required height, access, insulation, ventilation or conditioning requirements, utility routing and structural support |
| Excavation, drainage, access, wall and support design, stairs, utility locations and coordination with the home layout | Must be reviewed and approved for the specific home and property before construction |
Prepare the Driveway and Delivery Area
The driveway and delivery area should be prepared for the loads, dimensions and turning requirements identified by the mover.
Preparation may include:
- Widening the approach
- Improving the driveway surface
- Providing sufficient turning room
- Removing parked vehicles, equipment and materials
- Maintaining access during wet or changing conditions
- Keeping the path to the foundation unobstructed
- Providing staging space for contractors and equipment
The building mover and applicable site contractor should confirm the required preparation.
Clear the Site
Before delivery:
- Remove required trees and branches
- Clear debris and stored materials
- Address fences, gates or structures that interfere with access
- Confirm overhead clearance
- Maintain safe access around the foundation
- Confirm that delivery and placement equipment has sufficient operating space

Step 4: Prepare Utilities and Coordinate Your RTM Delivery
Plan Your Utilities
Utilities are typically not included as part of the RTM home itself. The homeowner should coordinate applicable services, including:
- Electrical service
- Water or well
- Sewer or septic
- Gas or other fuel service
- Communications services
- Heating and HVAC activation
- Required trenching, entry points or service equipment
Utility planning should begin early because service locations can affect the foundation and home design.
Confirm Utility Connection Locations
The homeowner, STAR and applicable contractors should confirm where services will enter the home. This may require coordination of:
- Electrical-entry location
- Mechanical-room layout
- Plumbing connections
- Well and septic placement
- Sewer and water connections
- Foundation penetrations
- Exterior equipment locations
Where a utility location affects the home layout, communicate the requirement during drafting rather than after construction.
Choose an Experienced Building Mover
Hire a mover with appropriate experience transporting and placing RTM homes.
Discuss the following items with your mover:
- Home dimensions and weight information available from STAR
- Pickup requirements
- Route feasibility
- Required permits within the mover’s scope
- Access and clearance requirements
- Placement method
- Equipment requirements
- Foundation readiness
- Weather or ground-condition considerations
- Insurance and contractual responsibilities
STAR may provide suggested vendors or referrals, but the homeowner should evaluate, hire and manage the mover.
Coordinate Everyone Involved
The homeowner acts as the communication hub between:
- STAR
- Building mover
- Foundation contractor
- Excavation or site contractor
- Electrician
- Plumber
- HVAC contractor
- Well or septic contractor
- Municipality or planning authority
- Utility providers
- External project manager, if hired

Step 5: Prepare for Delivery Day and Home Placement
Before the Home Arrives
Confirm that:
- The building mover has approved the route and site access
- The foundation is complete and ready for placement
- Required foundation inspections or approvals are complete
- The driveway and delivery area meet the mover’s requirements
- Trees and overhead obstacles have been addressed
- The site is clear of vehicles, equipment and materials
- Required contractors know the delivery schedule
- STAR’s release or pickup requirements are complete
- Contact information has been shared among all key parties
- A plan is in place for work immediately following placement
What Happens During Delivery
On delivery day, the building mover transports the home to the property and positions it on the prepared foundation using the mover’s approved process and equipment.
For the homeowner, this can be the project’s most memorable moment. When the planning is complete and the site is ready, delivery day can become an opportunity to watch the experienced crews do their work.
After Your STAR RTM Home Is Placed
Getting the home onto the foundation is a major milestone, but it is not necessarily the end of the project.
Depending on the contract and property, the homeowner may still need to coordinate:
- Securing or completing the home-to-foundation interface
- Electrical connection
- Water and sewer or well and septic connections
- Plumbing connection
- Heating and HVAC activation
- Required stabilization or protection of mechanical systems
- Stairs, decks, landings or exterior access
- Foundation finishing
- Interior or exterior finishing excluded from STAR’s scope
- Grading and drainage
- Local inspections
- Final permit sign-offs
- Occupancy approval, where required
The time required to make the home livable depends on site readiness, contractor coordination, inspections and the remaining work.
Your Complete STAR RTM Home Prepartion Checklist
Get the full checklist to help you stay organized from foundation to front door.
Download the ChecklistReady to Plan Your STAR RTM Home?